Status: concept stage. The design is complete. No land tenure is held, no approval has been granted, and no offtake is contracted.
A preferred site in the Top End of the Northern Territory is under assessment through the Crown land and Native Title processes, and the commercial terms of any tenure are not settled.
The figures on this page are reference-design values for a site of this kind. They will be re-established for the site that is secured, and they are not a commitment.
The project logo symbolises how the centre draws on the sun, and on water held on the site and harvested from rain. It harvests the sun's energy to power the data centre through the day; at night it draws on water stored in the upper reservoir; and it uses the same water to cool the centre's facilities.
The reference design
A 250 MW hyperscale data centre campus with 200 MW of IT load at a power usage effectiveness of 1.25, powered entirely from on-site generation and islanded: no grid connection, no import, no export, and no load on the Territory's transmission network.
The design is built on both brownfield and greenfield ground. The lower reservoir is a new 300 hectare embankment-berm; the upper reservoir is formed on the natural plateau above it, which is what makes long-duration storage economic at this scale. Working on both means the scheme causes less land disturbance than clearing an entirely new site.
Technical summary for tenants (PDF) — the configuration, the energy balance, the firmness cases and the current status, in two pages.
Reference configuration
| Data centre | 250 MW facility, 200 MW of IT load, PUE 1.25 |
|---|---|
| Solar | 1,400 MW, about 2,300 full-load hours a year — 3,220 GWh |
| Pumped hydro | 625 MW (five 125 MW reversible variable-speed Francis units), 9,194 MWh of storage |
| Upper reservoir | 250 ha on the natural plateau, formed by a perimeter berm over excavation; 35.38 M m³ active, plus 13.69 M m³ of dead storage below the operating minimum |
| Lower reservoir | A new 300 ha embankment-berm; 35.38 M m³ active |
| First fill | 49.07 M m³ to the weir, drawn from the site's own catchment |
| Battery | 100 MW / 50 MWh, for ride-through and island stability |
| Gas firming | 250 MW gas turbine, held as last-resort firming |
| Estimate class | Class 4 (±25–30%). Costing has been prepared and is available under confidentiality |
| Stage | Concept design complete |
Performance, stated plainly
Modelled over a 34-year record of measured rainfall and solar irradiance at the site.
| Renewable share | Approximately 98.7% of annual energy |
|---|---|
| Gas share | Approximately 1.3% of annual energy |
| Gas generation | Approximately 27.7 GWh a year, on about 29.5 days, almost all in June to August — for the hours those days need firming, not the whole day |
| Emissions | Approximately 11.9 kt CO2-e a year — 88% under the 100 kt Safeguard Mechanism threshold |
We do not claim 100% renewable energy, 24/7 carbon-free energy, or "renewable firming". When it is fully operational, the design runs on gas on approximately 29.5 days a year. Ahead of the pumped hydro completing, gas use is higher: until the reservoir fills, the campus runs on gas and solar. The gas share is declared, metered and reported — not offset.
What it would contribute
Modelled using the Infrastructure Australia method for direct employment, applied to this project's own cost structure and adjusted for the Northern Territory. The figures describe the contribution if the project is built as designed; they are not a commitment.
Construction would be sequenced around the wet season, when heavy earthworks are not possible. On the basis modelled for this assessment, direct employment would average about 3,700 full-time equivalents, peak at about 4,300 and total in the order of 9,200 job-years; these figures will be restated once the construction programme is fixed. Operations would support about 73 permanent roles on the energy assets. The data hall workforce belongs to the tenant and is not counted here.
The site falls within the Victoria Daly Regional Council. The campus would pay the prevailing rates, waste management and collection charges that apply at the time.
Basis: direct employment from the Infrastructure Australia top-down method, using its published multipliers, the Northern Territory regional adjustment and the FTE conversion factor, applied to the project's Class 4 cost estimate and an indicative construction profile. Indirect and induced employment are not claimed. Total capital cost and the construction expenditure profile are commercial-in-confidence and are not published.
Location and connectivity
The Northern Territory has become one of the more closely watched digital locations in Australia, for reasons that are geographic rather than promotional. The Territory Government places Darwin within 50 milliseconds of more than 500 million people, and measures the Darwin–Singapore path as the fastest from any Australian capital — about 2.4 times faster than from Sydney and 1.2 times faster than from Perth. Three new international digital connections are being established, and hyperscale operators are actively assessing the Territory.
The campus sits on the Stuart Highway corridor between Darwin and Katherine, the route of the Territory's principal fibre backbone, upgraded under the Terabit Territory programme from 400 Gbps to 20 Tbps. Darwin is becoming a landing point for international cables rather than a terminal one.
The combination is why the site was chosen: international latency, a national fibre corridor, an all-weather highway, and enough land and energy to build at scale without a capital city's land cost. No fibre connection is contracted — this describes the infrastructure the site sits on, not an arrangement we have made.

What the campus can host
The reference design is a 250 MW campus with 625 MW of pumped-hydro generating capacity behind it. It is built to carry its own load rather than to draw on a constrained grid.
| Generation | Five 125 MW reversible machines. With any one out of service, 500 MW remains against a 250 MW load — twice the requirement |
|---|---|
| Pumping | A single unit outage still delivers the daily recharge of 4,620 MWh inside the 8.4-hour window |
| Dead storage | 13.69 M m³ held below the operating minimum — about 39% of the 35.38 M m³ active volume — outside the daily cycle |
| Transfer and stability | A 100 MW / 50 MWh battery covers the transfer between pumping and generating and holds the island stable while the gas turbine starts |
| Isolation | No grid connection, so no dependence on a connection queue, a network upgrade or a third party's construction programme |
Gas: a firming reserve beside a world-scale gas province
Gas is the smallest part of this design — about 1.3% of annual energy, on roughly 29.5 days a year. But the project is fortunate in where it can buy it. The Beetaloo Sub-basin, south-east of Katherine, holds approximately 7.1 trillion cubic feet of publicly reported gross contingent resource (2C) of shale gas — of the order of 7,000 petajoules, or about 35 years of electricity for every home in Australia as energy in the ground.
Against a resource that size, the gas this project would use is a very small fraction of the reported reserve. The campus would take gas from one of the main transmission lines that run along the Stuart Highway corridor, through a short lateral connection into that line. It would not need a long-distance pipeline of its own.
Water
The scheme is a closed recirculating system: water is pumped between the two reservoirs and returned, so there is no consumptive use in the generation cycle. Losses are evaporation and seepage; water is not drawn from a river, borefield or town supply, and losses are replaced from rainfall and site runoff. On the current geometry the site supplies about 9.26 million cubic metres a year against a make-up requirement of about 2.97 million, leaving a margin of about 5.58 million — and it remains a live design item until the geological survey and seepage testing are done.
Status and next steps
The concept design is complete. Four workstreams stand between a design and a construction site, sequenced so that each de-risks the next.
- Land tenure. The Crown land and Native Title processes run in parallel, because both must conclude before a lease can be granted. Native Title consent is the critical path, and consent is sought before the project proceeds.
- Site survey. Plateau contour survey and geotechnical drilling, which convert the design's assumptions into measured values and come first, because storage volume and wetted surface depend on them.
- Environmental and heritage. Seepage and pit water quality testing, and cultural heritage assessment.
- Approvals. Environmental assessment by the Territory and the Commonwealth, with field work started early and lodgement as soon as the reports are complete. Assessment timing is determined by the regulators, not by the proponent.
Disclaimer
This page is a concept-stage summary prepared by Sunsurge Pty Ltd for information only. It describes a reference design, not a committed project: no land tenure, approval, finance or offtake is in place. It is not an offer, an invitation to invest, a commitment of funds, financial product advice or legal advice, and no reliance should be placed on it for an investment decision. Figures are indicative, are subject to survey, design development and the terms of any tenure, and may change. Actual results may differ, and Sunsurge Pty Ltd gives no warranty as to the accuracy or completeness of this information.